It is possible to transfer Projects, Tasks dates when Integrating projects from Web TimeSheet to Web Resource. To do so perform the following steps,

  • Log into Web Resource with administrative privileges.
  • Point to 'Administration' tab.
  • Click on 'Web TimeSheet Integration' option.
  • Click on 'Projects tab'.
  • Put a check mark on "Overwrite Web Resource project dates with Web TimeSheet project dates." (Please refer to the attached screenshot to the solution, 'Project – Task Dates.PNG'.)
  • Once above step is done, same information is reflected in the 'Summary' section that Project/Tasks dates will be overwritten.
  • Select other options as required to transfer project.
  • Click on 'Start Integration' to integrate the project.