Only Work-type resources can be transferred to Web TimeSheet; Cost and Material resources cannot be transferred. In addition, any Work resources marked as being either Budget or Generic resources will also not be transferred. This is because Budget resources are only available at a summary level in Project, and would therefore not be used to enter time against projects, and Generic resources are placeholders only.

Note: Do not attempt to transfer a project from Web TimeSheet that contains CostMaterialBudget, or Generic resources in Project. Since these users do not exist in Web TimeSheet (since they were not transferred initially), they will be deleted from Microsoft Project when the project is transferred.