When Update Task End Date is enabled under Advanced Settings in Microsoft Project Integration Manager, it transfers the following details:

  • The project or task's Finish date field in Project (located on the File > Properties > Contents tab) to or from…
  • The Time Entry End Date field in Web TimeSheet

If you are transferring a project from Web TimeSheet to Microsoft Project, start and end dates:

  • ARE updated, if it is the first transfer of that project. If you do not enable these options, the date of transfer will be transferred to these Project fields instead
  • ARE NOT updated, if it is the second (or subsequent) transfer of that project.

Note: Not updating these fields in this direction prevents data conflicts.