Scenario:

Task has been deleted from the project in Microsoft Project and the corresponding task in Web TimeSheet does not get deleted even after an update using MSPI (Microsoft Project Integration Manager).

 

Cause:

Verify if the task is selected on any user's timesheets. If the task has been selected on a user’s timesheet, Web TimeSheet prevents the task from being deleted, even if no time has been entered against it.

 

Resolution:

Have the user select another task or delete the timesheet row and then save the timesheet. Update Web TimeSheet using the Microsoft Project Integration Manager again and the task should be deleted from within Web TimeSheet.