Time transferred from Web TimeSheet to Microsoft Project are saved as Actual Work. To View the Total Actual Hours at the task level, follow the steps given below:

  •  Open the specific projects (.mpp) file.
  • In the Gantt Chart view right click on any of the column header.
  • Click Insert Column.
  • In the Column Definition window select Actual Work column from the Field Name drop-down.
  • Click OK.